Summarized from ST
13 May 2015
A NEW junior college (JC) slated to be completed in 2018 had to be delayed because of transport infrastructure being built underneath it, the Ministry of Education (MOE) learnt in 2013. In a letter to parents yesterday, the second it has sent about the delay, MOE said it was told this when the Land Transport Authority (LTA) wrote to it that year.
MOE will hold a dialogue with parents of affected students on May 25.
The construction timeline is revised from mid-2018 to end-2019, and parents and students were informed on April 13.
Yesterday, MOE said the delay was “not desirable”, but having both projects on the same site “ensures better use of our limited land resources”.
The as-yet unnamed JC, to be sited at the junction of Sin Ming Avenue and Marymount Road, will take in mainly Integrated Programme (IP) students from Catholic High, St Nicholas Girls’ and Singapore Chinese Girls’ schools.
– See more at: http://www.straitstimes.com/news/singapore/education/story/high-rise-junior-college-delayed-transport-works-beneath-site-moe-201#sthash.Lub56I4a.dpuf